DIVISIÓN CODELCO NORTE
| DIVISIÓN CODELCO NORTE | Inversión Estimada (Miles de US$) | ||
| DESCRIPCION | AÑO 2006 | AÑO 2007 | SGTES | 
| SERVICIOS E INFRAESTRUCTURA | 0 | 16.450 | 3.300 | 
| REEMPLAZO CARGADORES HORCAJADA | 0 | 1.000 | 1.000 | 
| REEMPLAZO CAMIONES ESCORIA | 0 | 2.100 | 0 | 
| REEMPLAZO GRUAS | 0 | 1.700 | 2.300 | 
| ADQUISICION CAMIONES DE SERVICIO | 0 | 4.950 | 0 | 
| ADQUISICION GRUAS HORQUILLAS | 0 | 6.700 | 0 | 
| INNOVACION E INVESTIGACION TECNOLOGICA | 2.143 | 6.320 | 139 | 
| CTROL OPTIMIZ FLOT PRIM Y LIMP PTA MOLY | 50 | 50 | 0 | 
| IMPLANTAC MOLIMAX CERTIFICACION RESULTAD | 100 | 200 | 0 | 
| PROTOTIPO MAQ AUX CAMBIO REVESTIMIENTOS | 200 | 600 | 0 | 
| FLOTACION FINOS Y ULTRAFINOS FASE II PBA | 150 | 350 | 0 | 
| LIXIV PRESION CONCENT MOLIB FAS II PR PI | 100 | 112 | 0 | 
| DESARR TECN DEPOS RELAV ESPESADOS | 100 | 200 | 0 | 
| RECUPERAC MO DESDE COLA MO FASE II | 100 | 100 | 0 | 
| SELECTIVIDAD MINA FASE II | 50 | 150 | 0 | 
| FITORREMEDIACION DE SUELDOS | 103 | 75 | 0 | 
| TOBERAS AUTOLIMPIANTES | 100 | 400 | 0 | 
| RECUPERACION ZINC APLICAC INDUST | 150 | 150 | 0 | 
| SISTEMA EXPERTO PREDICTIVO SIGNOS VITALE | 60 | 40 | 0 | 
| INTEGRACION MINA PLANTA FASE II | 60 | 30 | 0 | 
| AUTOMATIZACION MAQUINA DE CATOD RECHAZ | 220 | 242 | 0 | 
| EVALUAC Y VALIDAC PICKET FENCE TIPO DDG | 50 | 62 | 0 | 
| RECUPERAC MOLIB COBRE SULF FERRIC ESC FU | 50 | 58 | 0 | 
| LIS TOKI DISEÑO PRUEBA INDS ESTU ING | 500 | 1.200 | 0 | 
| MINERALOGIA EN LINEA - FASE IV | 0 | 100 | 0 | 
| PLAN DE ACCIONES TECNOLOG APOYO P1 DCN | 0 | 200 | 0 | 
| FLOTACION DE FINOS Y ULTRAFINOS | 0 | 500 | 0 | 
| SIST REBOTIZADO LIMP HORNO TOST IMPLANT | 0 | 100 | 0 | 
| SIST ROBOTIZADO LIMP HORNO TOST CERT RES | 0 | 50 | 0 | 
| USO DESECHOS DE CAL DE CTM EN CONC. | 0 | 60 | 0 | 
| SELECT PEBBLES SAG VALIDAC HIP DIST LEYE | 0 | 100 | 0 | 
| COLECTORES CONCENTRICOS PARABOLICOS | 0 | 250 | 0 | 
| MAGNETO CATALIZADORES | 0 | 150 | 0 | 
| ESTUDIO USO HIDROGENO EN DCN | 0 | 100 | 0 | 
| CAIDA DIENTE PALA | 0 | 90 | 10 | 
| CAMION VLT DEVOLUCION KOMATSU | 0 | 150 | 0 | 
| SIST EXPERTO PREDICT SIGNOS VITALES PALA | 0 | 100 | 0 | 
| INTEGRACION MINA - PLANTA FASE III | 0 | 30 | 0 | 
| RIPIOS SUBYACENTES RMS FASE II | 0 | 321 | 129 | 
| GASTOS DIFERIDOS | 135.803 | 159.667 | 157.639 | 
| TRASLADO CALAMA | 123.605 | 3.110 | 0 | 
| DESCARGA LASTER PARED OESTE | 12.198 | 30.800 | 0 | 
| DESARROLLO MINA CHUQUICAMATA | 0 | 123.757 | 157.389 | 
| RECONOCIMIENTO GEOLOG SECT MINA CHQU | 0 | 2.000 | 250 | 
| INVERSIONES VIA API SEGÚN GASTO | 232.150 | 487.041 | 185.926 | 
| CAMBIO TECNOL PROCESO ELECTRO-REFINAC | 33.690 | 1.163 | 0 | 
| MEJORAM SIST ALUMBRADO INSTALAC GCIA REF | 1.024 | 601 | 0 | 
| Sistema Drenaje ENMS Fase II y III | 11.454 | 7.084 | 0 | 
| EIMINCO FURE | 42.028 | 199.163 | 6.665 | 
| ING BAS MEJ CON SUB SALA BATERIAS S/E AT | 269 | 0 | 0 | 
| ING BAS MEJ COND SUB ILUM S/E A.T. CHUQU | 216 | 0 | 0 | 
| CAMBIO TECNOL PROCESO ELECTRO-REFINAC | 3.500 | 187 | 0 | 
| MEJORAM SIST ALUMBRADO INSTALAC GCIA REF | 0 | 155 | 0 | 
| Sistema Drenaje ENMS Fase II y III | -1.209 | 1.208 | 0 | 
| EIMINCO FURE | -802 | -2.756 | 3.567 | 
| ING BAS MEJ CON SUB SALA BATERIAS S/E AT | -61 | 61 | 0 | 
| ING BAS MEJ COND SUB ILUM S/E A.T. CHUQU | -53 | 53 | 0 | 
| ALMACENAM ACIDO SULFURICO CORPORATIVO CN | 5.831 | 5.529 | 0 | 
| REEMP 4 PALAS 34 YD3 MINA CHUQUICAMATA | 31.946 | 411 | 0 | 
| REEMP SISTEMA ADITIVOS EN REFINERIA 2 | 1.314 | 345 | 0 | 
| AUMENTO FLOTA PALAS 2007 MINA RT | 60 | 16.265 | 886 | 
| AUMENTO FLOTA PERFORAD 2007 MINA RT | 77 | 4.086 | 0 | 
| ADQUISICION BARRAS EQUIPOTENCIALES | 833 | 267 | 0 | 
| MEJ COND SUB SIST ELEC FLOTAC A0 Y MOLIE | 180 | 9.575 | 905 | 
| MODERNIZ SIST CTROL MOL SAG CONCENT A2 | 651 | 3.158 | 4.106 | 
| ITEM 1 DELINEAM EXPLOTACION SULFUROS RT | 8.022 | 7.472 | 0 | 
| ITEM 2 EST ING EXPLOTACION SULFUROS RT | 1.894 | 476 | 0 | 
| ACIDUCTO A TERMINAL DE ACIDO CN | 1.457 | 2.642 | 0 | 
| EXPL.Y EVAL.HIDROG DE CACHIMBA | 1.760 | 244 | 0 | 
| EXPL HIDROGEOLOG SECTOR NORESTE TALABRE | 1.694 | 163 | 0 | 
| ELIMNACION CONDIC SUBEST TERMINAL ACIDO | 1.052 | 4.461 | 0 | 
| HABILITACION CASINO INDUSTRIAL CHUQUI | 1.037 | 1.034 | 258 | 
| REEMP MAQ ENLAINADORA MOL BARRA CONC A2 | 800 | 413 | 0 | 
| AUM CAP TRANQUE TALABRE VI ETAPA MUROS | 974 | 15.931 | 29.223 | 
| ING.PERFIL Y EXPL.AVAN. MM SBTERRANEA | 13.200 | 8.800 | 0 | 
| INGENIERIA DE PERFIL CLUSTER TOKI | 5.000 | 12.300 | 0 | 
| REEMP PESOMET Y CORTAD MUESTRAS CORR AL | 725 | 4.295 | 541 | 
| ACTUALIZACION PERFORADORAS 4 x 3 CN DMH2 | 46 | 12.129 | 0 | 
| CONST CHIM Y SIST VENTILAC CAVER CHAN M1 | 2.178 | 2.172 | 541 | 
| ADQ GRUA UNIDAD REPARAC COMP MAYOR MINA | 37 | 1.136 | 0 | 
| TRASLADO INSTALAC POR EXPANSION 38 SUR D | 1.290 | 3.470 | 0 | 
| AMPLIACION NAVES CAMIONES RT | 56 | 2.746 | 0 | 
| AUMENTO FLOTA CAMIONES PND 2006 | 44.728 | 18.388 | 0 | 
| LIX SECUNDARIA RIPIOS FASE V | 13.011 | 10.000 | 0 | 
| LIXIVIACION MINERALES OBL DUMP 3 | 2.242 | 15.691 | 0 | 
| SISTEMA AISLAMIENTO SILOS MOLIENDA CONV | 0 | 1.533 | 0 | 
| NORMALIZACION CON SUBEST TUNELES ELEC | 0 | 397 | 595 | 
| NORMALIZAC SISTE ELECT EMERGENC PTA CONC | 0 | 500 | 2.500 | 
| ING CONC REEMPL Y AUTOM VALVULA AUMAC | 0 | 450 | 0 | 
| SISTEMA DRENAJE MINA CHUQUI, FASE II | 0 | 2.500 | 12.500 | 
| MODELO RIESGO GEOTECNICO MINA CHUQ | 0 | 800 | 3.500 | 
| DELINEAC Y DESCARTE HIDROG SECT CORD MED | 0 | 1.000 | 800 | 
| ESTUDIO ALTERNATIVAS TRANQUE RELAVE | 0 | 1.000 | 800 | 
| CONSOLIDACION HIDROGEOLOGIA ASCOTAN NOR | 0 | 600 | 0 | 
| ESTUDIO ALTERNATIVAS TRANQUE RELAVE | 0 | 1.500 | 1.000 | 
| MODELO HIDRAUL RIO LOA TRAM ALTO Y BAJO | 0 | 400 | 1.300 | 
| PLAN ESTRAT EXPLORACION PEX PND FASE I | 0 | 2.500 | 3.000 | 
| ING BAS SULF RT SECTOR SUR CENTRAL NORT | 0 | 4.000 | 10.000 | 
| REEMPLAZO EQUIPOS ESPECIALIZADOS LOB | 0 | 1.000 | 1.100 | 
| CORREDOR BIOLOGICO DEL RIO SAN PEDRO | 0 | 1.200 | 0 | 
| ING CONC CONS 2DO VERT RESID INDU NO PEL | 0 | 500 | 0 | 
| OBRAS CIVILES DE MEJORAM REPOSIC RUTA 50 | 0 | 6.000 | 5.000 | 
| ING CONC LOGISTICA INTEGRAL | 0 | 250 | 0 | 
| ING CONC ALIMENTACION AGUA PND | 0 | 2.200 | 0 | 
| ING CONC REUBICACION PONDS SX | 0 | 200 | 0 | 
| NG PERFIL Y PRUBAS PILOTO LIS BOT 67 | 0 | 600 | 900 | 
| ING CONC DUMP OXIDOS MM | 0 | 800 | 0 | 
| ING PERFIL SULFUROS RT | 0 | 1.000 | 1.500 | 
| ING PERFIL CLUSTER TOKI | 0 | 3.000 | 1.000 | 
| ING BAS LIXIV RIPIOS SUBYACENTES | 0 | 200 | 0 | 
| ING BAS LIXIVIAC RENMS EN MEZCLA CON RCH | 0 | 800 | 0 | 
| ING LIXIVIACION DE RMS EN MEZCLA RCHUQUI | 0 | 250 | 450 | 
| ING BAS AUMENT CAPAC CANCHA RIPIOS RT | 0 | 350 | 0 | 
| ING BAS AUMENT CAPAC CANCHA RIPIOS ENMS | 0 | 350 | 0 | 
| ING BAS DUMP 3 | 0 | 500 | 0 | 
| ING CONC PROCESAMIENTO DE ARF | 0 | 1.500 | 0 | 
| ING BAS REEMP PRECIP ESLEC-VTA PTA AC 2A | 0 | 186 | 0 | 
| REEMP COMP PRECI MILJO CTE 2 | 0 | 750 | 0 | 
| ING BAS MEJORAM H ELEC Y PTA GRANALLA | 0 | 500 | 0 | 
| REEMPLAZO CASCO CPS 6 | 0 | 200 | 1.000 | 
| REEMP TRACTO NEUM 610 611 | 0 | 1.490 | 0 | 
| REEMP MOTONIVELADORA 790 | 0 | 582 | 0 | 
| REEMP CAMION CARGADOR | 0 | 1.300 | 0 | 
| AUMENTO CAMION REGADOR | 0 | 1.300 | 0 | 
| AUMENTO TRACTOR NEUMATICO 824 | 0 | 1.200 | 0 | 
| AUMENTO TRACTOR ORUGA TIP 475A | 0 | 1.400 | 0 | 
| AUMENTO MOTONIVELADORA TIPO 24H | 0 | 1.100 | 0 | 
| AUMENTO RETROEXCAVADORA | 0 | 600 | 0 | 
| REEMP. MANIPULADOR DE NEUMÁTICOS 4X4 | 0 | 2.000 | 800 | 
| REEMP PERFORAD CONTROL PARED | 0 | 1.500 | 0 | 
| AUMENTO MANIPULADOR NEUMATICO | 0 | 1.400 | 0 | 
| REFACCION ESTRUCTURA TOLVA GRUESA | 0 | 800 | 0 | 
| RETROEX B LARGO C MARTILL BALDE ASEO TAZ | 0 | 700 | 0 | 
| TRASLADO EQUIPOS CAVERNA TÚNEL SERV CHAN | 0 | 500 | 1.000 | 
| ALTERNAT NUEVO LAY-OUT REPASO SECC D Y E | 0 | 500 | 1.500 | 
| REDUCC GRANULOMET CHANC SEC-TERC | 0 | 500 | 3.000 | 
| ING BAS AUTOMATIZACION CARROS REPARTIDOR | 0 | 180 | 0 | 
| OVERHAUL CARGADOR FRONTAL 880 | 0 | 600 | 0 | 
| AMPLIACION NAVES CAMIONES RT | 0 | 800 | 2.200 | 
| SISTEMA ILUMINACION PLANTAS Y MINAS | 0 | 1.000 | 2.000 | 
| INFRAESTRUCTURA TALLER COMPONENTES MAYOR | 0 | 1.532 | 0 | 
| REEMP RED HUMEDA PLANTAS REF | 0 | 200 | 1.300 | 
| OVER HAUL GRUAS NAVE CENTRAL REF N 2 | 0 | 100 | 600 | 
| REFUERZ ESTR VIGAS Y COLUM CELD | 0 | 200 | 2.300 | 
| ING BAS TRAMIENTO IMPUREZAS REFINERIAS | 0 | 600 | 0 | 
| ING BAS SUSTENTABILIDAD AREA LIX Y TOS | 0 | 250 | 0 | 
| REEMPLAZO FLOTA CAT 793C | 0 | 21.000 | 21.000 | 
| REEMPLAZO PERFO 101 | 0 | 3.500 | 0 | 
| REEMPLAZO CARGADOR L 1400 | 0 | 4.500 | 0 | 
| AUMENTO FLOTA CAEX 5 KON 930E | 0 | 7.500 | 10.000 | 
| MEJ CONDI SUBEST ILUMINAC SUBESTAC AT | 0 | 260 | 740 | 
| MEJ COND SUBESTAND SALAS BATERIAS | 0 | 260 | 740 | 
| ING CONC REEMP EQU SUBESTAC ALTA TENS | 0 | 162 | 0 | 
| TRASLADO TALLERES SUPTCIA RECH HIDR | 0 | 720 | 0 | 
| ING BAS REPOSICION ACTIVOS | 0 | 578 | 0 | 
| MEJORAMIENTO CALIDAD DEPOS CATOD EN EW | 0 | 100 | 900 | 
| UP GRADE SISTEMA TRASPORTE RIPIOS | 0 | 3.074 | 7.173 | 
| MEJORAM SISTE EXTRAC GASES NAVE EW | 0 | 220 | 1.278 | 
| INGENIERIA BASISCA DUMP 3 | 0 | 600 | 0 | 
| MEJORAMIENTO SISTEMA CONTRA INCENDIO HN | 0 | 100 | 1.100 | 
| TRASLADO Y MEJORAM MAQUINAS NAVE EW | 0 | 2.000 | 1.500 | 
| INTERFERENCIA ENMS FASE IX | 0 | 2.000 | 26.508 | 
| CAMBIO DE 200 CELDAS EW HS | 0 | 1.000 | 1.200 | 
| REFACCION ESTRUCTURA NAVE EW HS | 0 | 2.000 | 0 | 
| MEJORAMIENTO RED CONTRAINCEND PTA SX HS | 0 | 2.000 | 2.200 | 
| ING BASICA MEZCLA RHQ RMS | 0 | 250 | 450 | 
| ING BASICA ALIMENTAC CAPAC CANCHA RIPIOS | 0 | 350 | 0 | 
| ING CONCEPTUAL OXIDOS MM | 0 | 800 | 0 | 
| ING CONCEPTUAL REUBICAC POND PLS | 0 | 200 | 0 | 
| ING PERF Y PRUE PILOT LIX IN SITU BOT 67 | 0 | 600 | 900 | 
| ING BAS LIXI BOTADEROS RBL Y J1 | 0 | 900 | 1.900 |